Creating new progress bills for jobs

When you create a new progress bill for a job, you can enter the scheduled costs for each cost code or division in the Scheduled column. After saving the first application, Sage 100 Contractor does not allow any changes to the scheduled costs unless the Allow Editing Scheduled $ option is selected. On subsequent applications, enter changes to costs in the Changes column.

In the Current Stored column, you can enter the amount of material currently being stored. When you create the next application, Sage 100 Contractor moves the costs from the Current Stored column to the Previous Stored column. As you complete work, remove the costs for items no longer being stored. To remove costs, enter the costs as a negative amount.

To create a new progress bill for a job:

  1. Open 3-7 Progress Billing.
  2. In the header:
    1. In the Job text box, enter the job number.
    2. If the job uses phases, enter the phase number in the Phase text box.
    3. In the Description text box, enter a brief statement about the work completed.
    4. If you want this billing to include all the phases for the job, select the Combine phases into single application checkbox before you import the budget or proposal.

      Note: Costs for all phases will be combined when you update costs.

    5. If you want to include this progress billing in the 6-12 Project Work Center, select the Hot List checkbox.
    6. In the Application# text box, enter the number of the application you are submitting.
    7. In the Billing Date text box, enter the date ending the period for which you are submitting the request.
    8. In the Billing Cycle text box, enter the billing cycle.
    9. In Sage 100 Contractor, a cycle is represented by ##DY (a number of days), ##MO (a number of months), and ##TH (a specified day every month). You replace the ## symbols with the number of days or months, or the day of the month for the processing cycle. For example:

      • 30DY means due every 30 days.
      • 02MO means due every two months.
      • 25TH means due on the 25th day of each month. Sage 100 Contractor displays the 25th of the month following the invoice date when you enter a new invoice for a vendor

    10. In the Submitted text box, enter the submittal date.
    11. In the Approved text box, enter the approval date.
  3. Under Billing Basis, select the Bill by cost codes or Bill by cost divisions option.
  4. On the Options menu, click Setup and complete the Progress Billing Setup window.
  5. Do one of the following:
    • On the Options menu, select Import, then click Import Budget.
    • On the Options menu, select Import, then click Import Proposal.
  6. In the grid, for each item:
    1. In the Current Completed text box, you can enter the costs incurred. If you provide the costs incurred, do not provide the percent of work completed in the % Completed text box.

    2. In the Retention Rate text box, you can accept the default primary rate from the Progress Billing Setup window, or you can enter a different rate for the item.

    3. In the Current Stored text box, enter the current cost of materials stored for the job.

    4. In the % Completed text box, you can enter the percent of work completed. If you provide the percent of work completed, do not provide the current costs incurred in the Current Completed text box.

    5. In the Taxable text box, type Yes if the item is taxable or No if the item is non-taxable.

  7. On the menu bar, click Calculate to select one option in the Calculate Grid window, then click [Calculate].
    1. Calculate the Current column based on the amounts entered in the Percentage column (this is based on the amount entered in the % Completed text box in step 10e)
    2. Calculate the Percent column based on the amounts entered in the Current and Stored columns (this is based on the amounts entered in the Current Completed and Current Stored text boxes in step 10a and 10c, respectively)

Note: Sage 100 Contractor creates a separate series of applications for each phase.